Overdue for an Update

I have started moving in!  I have been sleeping in the tiny house since my mattress was delivered at the beginning of the month.  It has been glorious to wake up in my loft, hearing the birds outside and feeling so very much at home!  The bathroom isn’t finished yet, there is no electricity and the propane hasn’t been installed yet, up until yesterday there was nothing to sit on and the floors were covered up with cardboard.

Here’s a recap of the work that has been done in the month since my last update:

The bathtub has been built!  The drain was installed, but leaked, so we had to head back to the drawing board and after some consultation and a new drain basket, fingers crossed, I will have a functional tub at the beginning of June.    Here are the tub progress pics.

The toilet bench has also been built.  The final coat of paint is drying as I type this.  The toilet bench also accommodates the winter grey water tank and the fancy grey water plumbing.  I have to attach the piano hinge for the two lids on the bench (one for the toilet and the other for the grey water compartment).  The sawdust will live in a bin that will rest on the grey water compartment.  The toilet will be ready early next week.

The kitchen counter has been installed!  I am really happy with the counter I chose and with the amount of counter there is in the tiny house.  The kitchen sink and faucet were installed and the freshwater plumbing is almost finished, with the exception of the countertop water inlet connection.  As it’s spring, I am all hooked with a potable water hose and I have running water.  The exterior grey water tank or french drain still has to be worked out, but as I am not living in the house full-time yet, it hasn’t been a problem yet.

The HRV units got their boxes, which we filled with spray foam, and then they were finished.  I am really happy with how the HRV units look and I get a bonus space above them to sneak in a knick-knack if the fancy strikes me.

Left to do (nb: this is not an ordered list)

  • Get a welder to come out and weld on the brackets for the propane tanks.
  • Get propane installed.
  • Install the stove and the furnace.
  • Finish the freshwater plumbing.
  • Install the drain and faucet on the tub.
  • Install the lids on the toilet bench.
  • Install ¼” plywood on the front edges of the rafters for the roofers.
  • Get a new roof.
  • Figure out my clothing storage.
  • Install the last of the trim in the bathroom.
  • Install the medicine cabinet in the bathroom.
  • Have a house-warming party!
Advertisements

12 thoughts on “Overdue for an Update”

  1. The counters are 21 ⅞” deep and the counter is 23″ deep. I wanted to be sure that there was enough space between the counters so that 2 people can work or hang out in the kitchen and so that if someone is working in the kitchen, the bathroom is still accessible.

  2. Wow, truly impressive Natalie, you should be very proud of this accomplishment. Inspirational! Congratulations on your lovely little home. Donna and Paul Verrall

  3. selfmade japanese hottub.. awesome!
    is it just wood and some glass and glue? how many layers did you put on and how did you paint it? seems like a lot of work to me!
    but def. worth it!
    my deepest respect from austria.
    erik

    1. Thank you Erik,

      The tub is made of plywood, fibreglass and epoxy/resin. It has 3 layers of fibreglass and resin but it could have been fewer layers if the fibreglass had been heavier. The tub is painted with marine paint.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s